Installation

The major benefit when fitting E-Brick panels is that they are easy, quick and clean. The stages of installation when fitting E-Brick panels are described below.

Stage 1:

stap11.jpg

Fit a corner slip to the wall so that you start from a flat, clean base. The E-Brick system can be fitted to almost any existing outside wall.

Stage 2:

stap21.jpg

Separate insulating corner slips are screwed on to cover the corners of the wall.

Stage 3:

stap3.jpg

Attach the E-Brick panels using stainless steel screws in the holes provided. The holes are drilled during manufacture. As standard, holes must be drilled for 9 screws. The higher the location of the work to be carried out, the higher the number of holes.

Stage 4:

stap4.jpg

Apply silicon to the joints between the E-Brick panels to garantee all is waterproof.

Stage 5:

stap5.jpg

The corners of the wall, windows and doors are finished with corner slips supplied in the same colour of brick. Connecting slips are also fitted between individual E-Brick panels to finish the wall off. These slips and corner pieces are sustainable glued to the insulating layer.



Stage 6:

stap6.jpg

When all panels, connecting slips and corner pieces have been fitted, the ensemble is pointed with a grouting produce of the desired colour.